Course Objective
Scheduling and cost control are essential tools for successful construction management. Scheduling deals with network based schedules of construction activities (like critical path method) and cost control provides comparison of actual and planned financial information in the course of the project. Time extension claims in construction contracts wherein the proof of cause-effect relationship is the essence of the whole argument are currently required to be submitted together with construction schedules like critical path method.To furnish the civil engineering students with this skill set a popular computer software for construction scheduling and cost control shall be taught thoroughly in this course.
Course Content
Introduction and some advanced studies in a computer application like MS Project, extensively used for construction scheduling and cost control; time extension clauses in international construction contracts; cause-effect relationship to prove construction claims.
Prerequisites
CE399
Delivery and Teaching Methods
- Face to face
- Lecture
- Question and answer
- Problem solving
Learning Outcomes and Contribution to Programme Outcomes
- 1• To develop the ability to schedule construction projects like any other industrial, commercial or office works.
- 2• Present achieved progress in a variety of formats ranging from a simple bar chart to more complicated network type diagrams.
- 3• Present cost data in graphic form or as summarized in tables.
- 4• Check and verify time-wise and financial success of the project during performance.
- 5• Manage costs, work and resources used in the project.
- 6• Types of delays and acceptable reasons for time extensions in international construction contracts.
- 7• How to implement construction schedules to prove loss-expense and time extension claims.
Weekly Topics
| Week | Topic |
|---|---|
| 1 | What is scheduling and cost control in construction management . |
| 2 | Types of scheduling techniques |
| 3 | Types of scheduling techniques |
| 4 | Precedence relationships and critical path method |
| 5 | Precedence relationships and critical path method |
| 6 | Preparing the list of construction activities ( teaching the computer application) |
| 7 | Specifying construction resources |
| 8 | Assigning resources to activities |
| 9 | Formatting and sharing the plan |
| 10 | Tracking progress on activities |
| 11 | Advanced windows showing activity details |
| 12 | Advanced windows to assign resources to activities |
| 13 | Time extensions in construction conditions. Liquidated damages as opposed to penalties. |
| 14 | Time extensions in construction conditions. Liquidated damages as opposed to penalties. |
| 15 | Final Exam Period |
| 16 | Final Exam Period |
Assessment
| Method | Number | Weight |
|---|---|---|
| Finalexam | 1 | %30 |
| Midtermexam | 2 | %50 |
| Lab | 6 | %20 |
| Total | %100 | |
ECTS Workload
| Activity | Number | Duration (hours) | Total |
|---|---|---|---|
| Lecture Hours (Including exam week: 16 x lecture hours) | 16 | 3 | 48 |
| Midterm Exam Preparation | 2 | 12 | 24 |
| Final Exam Preparation | 1 | 18 | 18 |
| Out-of-Class Study Time | 14 | 3 | 42 |
| Laboratory | 6 | 3 | 18 |
| Total workload (hours) | 150 | ||
| ECTS equivalent (workload / 30) | 5 | ||
Resources
- Textbook Microsoft Project 2010, Step by Step, Carl Chatfield and T. Johnson, Microsoft Press, Washington
- Other Powell-Smith, V, J. Redmond and D. Stephenson, “ Civil Engineering Claims”, 1999, 3 rded, Blackwell Science Ltd, Oxford